Amelia has the following requirements: Three separate functional teams need to work on a single company-managed project. Each team must focus on its issues without needing complex configuration. Each team needs to visualize its progress using a Burnup Chart showing only its issues. As a project administrator of a company-managed project, which configuration is the most appropriate to meet all of Amelia’s requirements?