Video: You have received the following requirements: Two jira video

Question 1 Be Honest
« Back   Next managing-projects-acp-620 Certification Question »
Answer

Full Certification Question

You have received the following requirements: Two separate development teams need to work in a single company-managed project Each team has to focus on its own issues without a need for complex configuration Each team needs to identify potential bottlenecks using a Cumulative Flow Diagram showing only its own issues The manager of both teams needs a unique Burndown Chart showing the overall progress of both teams As a project administrator of a company-managed project, which configuration is the most appropriate to meet all these requirements?