As a project manager, Dom is responsible in jira video

 ·  PT1H46M27S  ·  EN

managing-projects-acp-620 video for as a project manager, Dom is responsible in monitoring all issues that have been assigned to his team are on track and the

Full Certification Question

As a project manager, Dom is responsible in monitoring all issues that have been assigned to his team are on track and the Time Estimation for each issue is correctly measured. Which of the following is the best report that he can use to ensure Time Estimation and Time Spent by his team on issues are on track?