This is a dedicated watch page for a single video.
Dylan has started a sprint with 5 issues. All issues are in the To Do column. He then made the following actions: The first day of the sprint, he moved 2 issues to In Progress Column The second day of the sprint, he moved 1 issue from In Progress to Done Column The third day of the sprint, he took 1 issue out of the Done column and move it back to To Do Considering that each column is mapped to a status of the same name and that the right-most column is ‘Done’ and that the left-most column is ‘To Do’, what will the Cumulative Flow Diagram show?