Video upload date:  · Duration: PT1H46M27S  · Language: EN

You are the project manager of the QPS project isaca video

crisc video for you are the project manager of the QPS project. You and your project team have identified a pure risk. You along with the key stakeholders,

This is a dedicated watch page for a single video.

Full Certification Question

You are the project manager of the QPS project. You and your project team have identified a pure risk. You along with the key stakeholders, decided to remove the pure risk from the project by changing the project plan altogether. What is a pure risk?