crisc video for diana is the project manager of the QPS project for her company. In this project Diana and the project team have identified a pure risk. Diana

Full Certification Question

Diana is the project manager of the QPS project for her company. In this project Diana and the project team have identified a pure risk. Diana and the project team decided, along with the key stakeholders, to remove the pure risk from the project by changing the project plan altogether. What is a pure risk?