Henry is the project manager of the QBG Project isaca video

crisc video for henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to

This is a dedicated watch page for a single video.

Full Certification Question

Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. TheCIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work. What component of the change control system would review the proposed changes' impact on the features and functions of the project's product?