You are the project manager of the NNQ Project isaca video
crisc video for you are the project manager of the NNQ Project for your company and are working with your project team to define contingency plans for the risks
            Question 1
            Be Honest
          
          
        Answer
          Full Certification Question
You are the project manager of the NNQ Project for your company and are working with your project team to define contingency plans for the risks within your project. Mary, one of your project team members, asks what a contingency plan is. Which of the following statements best defines what a contingency response is?