You are the project manager of the NNH project isaca video

crisc video for you are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should

This is a dedicated watch page for a single video.

Full Certification Question

You are the project manager of the NNH project. In this project you have created a contingency response that the cost performance index should be less than0.93. The NHH project has a budget at completion of $945,000 and is 45 percent complete - though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's cost performance index?