crisc video for tracy is the project manager of the NLT Project for her company. The NLT Project is scheduled to last 14 months and has a budget at completion

Full Certification Question

Tracy is the project manager of the NLT Project for her company. The NLT Project is scheduled to last 14 months and has a budget at completion of $4,555,000.Tracy's organization will receive a bonus of $80,000 per day that the project is completed early up to $800,000. Tracy realizes that there are several opportunities within the project to save on time by crashing the project work. Crashing the project is what type of risk response?