Marsha is the project manager of the NHQ isaca video

crisc video for marsha is the project manager of the NHQ Project. There's a risk that her project team has identified, which could cause the project to be late

This is a dedicated watch page for a single video.

Full Certification Question

Marsha is the project manager of the NHQ Project. There's a risk that her project team has identified, which could cause the project to be late by more than a month. Marsha does not want this risk event to happen so she devises extra project activities to ensure that the risk event will not happen. The extra steps, however, will cost the project an additional $10,000. What type of risk response is this approach?