You are the project manager of the NHQ project isaca video
crisc video for you are the project manager of the NHQ project in Bluewell Inc. The project has an asset valued at $200,000 and is subjected to an exposure
            Question 1
            Be Honest
          
          
        Answer
          Full Certification Question
You are the project manager of the NHQ project in Bluewell Inc. The project has an asset valued at $200,000 and is subjected to an exposure factor of 45 percent.If the annual rate of occurrence of loss in this project is once a month, then what will be the Annual Loss Expectancy (ALE) of the project?