crisc video for you are the project manager of the NHQ project in Bluewell Inc. The project has an asset valued at $200,000 and is subjected to an exposure

Full Certification Question

You are the project manager of the NHQ project in Bluewell Inc. The project has an asset valued at $200,000 and is subjected to an exposure factor of 45 percent.If the annual rate of occurrence of loss in this project is once a month, then what will be the Annual Loss Expectancy (ALE) of the project?