Video: You are the project manager of the NHQ Project isaca video

Question 1 Be Honest
« Back   Next crisc Certification Question »
Answer

Full Certification Question

You are the project manager of the NHQ Project for your company. You are discussing some of the project issues that need to be resolved in the project. You and the project stakeholders come to an agreement about the risk issues and how they will be resolved. Where should you document this information for issue resolution?