Full Certification Question

You are the project manager of the NHH Project. You are working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team.What document do you and your team is creating in this scenario?