John is the project manager of the HGH Project isaca video

crisc video for john is the project manager of the HGH Project for her company. He and his project team have agreed that if the vendor is late by more than ten

This is a dedicated watch page for a single video.

Full Certification Question

John is the project manager of the HGH Project for her company. He and his project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor. What type of response does John adopt here?