Video upload date:  · Duration: PT1H46M27S  · Language: EN

You are the project manager of the GHY project isaca video

crisc video for you are the project manager of the GHY project. In your organization you must follow certain enterprise environmental factors that establish the

This is a dedicated watch page for a single video.

Full Certification Question

You are the project manager of the GHY project. In your organization you must follow certain enterprise environmental factors that establish the rules for risk management . One of the policies your project must adhere to requires periodic rapid analysis of risks within the project. These rapid, cost-effective session must be documented and performed monthly. What type of analysis are you required to perform according to your enterprise environmental factors?