You are the project manager of the GHY Project isaca video
crisc video for you are the project manager of the GHY Project for your company. You need to complete a project management process that will be on the lookout
            Question 1
            Be Honest
          
          
        Answer
          Full Certification Question
You are the project manager of the GHY Project for your company. You need to complete a project management process that will be on the lookout for new risks, changing risks, and risks that are now outdated. Which project management process is responsible for these actions?