Certification Practice Exams with Real Test Questions & Answers

You are the project manager of the GHG project isaca video

 ·  PT1H46M27S  ·  EN

crisc video for you are the project manager of the GHG project for your company. You have identified the project risks, completed qualitative and quantitative

Full Certification Question

You are the project manager of the GHG project for your company. You have identified the project risks, completed qualitative and quantitative analysis, and created risk responses. You also need to document how and when risk audits will be performed in the project. Where will you define the frequency of risk audits?