Gary has identified a project risk that could isaca video

crisc video for gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become

This is a dedicated watch page for a single video.

Full Certification Question

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?