Full Certification Question

You are project manager for ABD project. You, with your team, are working on the following activities:✑ Probabilistic analysis of a project.✑ Probability of achieving cost and time objectives.✑ Trends in Qualitative Risk Analysis results.On which of the following processes are you working on?