crisc video for don is the project manager of the PFO project for his organization. Don is working with the project team members and two subject matter experts

This is a dedicated watch page for a single video.

Full Certification Question

Don is the project manager of the PFO project for his organization. Don is working with the project team members and two subject matter experts to assess the identified risk events in the project. Which of the following approaches is the best to assess the risk events in the project?