Video upload date:  · Duration: PT1H46M27S  · Language: EN

You are working as the project manager of the isaca video

crisc video for you are working as the project manager of the ABS project. The project is for establishing a computer network in a school premises. During the

This is a dedicated watch page for a single video.

Full Certification Question

You are working as the project manager of the ABS project. The project is for establishing a computer network in a school premises. During the project execution, the school management asks to make the campus Wi-Fi enabled. You know that this may impact the project adversely. You have discussed the change request with other stakeholders. What will be your NEXT step?