Full Certification Question

You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You have completed identifying all possible risks along with the stakeholders and team and have calculated the probability and impact of these risks. Which of the following would you need next to help you prioritize the risks?