Video upload date:  · Duration: PT1H46M27S  · Language: EN

You are the project manager of a large isaca video

crisc video for you are the project manager of a large networking project. During the execution phase the customer requests for a change in the existing project

This is a dedicated watch page for a single video.

Full Certification Question

You are the project manager of a large networking project. During the execution phase the customer requests for a change in the existing project plan. What will be your immediate action?