Tom is the project manager for his organization isaca video

 ·  PT1H46M27S  ·  EN

crisc video for tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that

Full Certification Question

Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baselines. Why would the risk response planning cause Tom the need to update the cost and schedule baselines?