Video: David is the project manager of HGF project for isaca video

Question 1 Be Honest
« Back   Next isaca Cloud crisc Question »
Answer

Full Certification Question

David is the project manager of HGF project for his company. David, the project team, and several key stakeholders have completed risk identification and are ready to move into qualitative risk analysis. Tracy, a project team member, does not understand why they need to complete qualitative risk analysis. Which one of the following is the best explanation for completing qualitative risk analysis?