crisc video for you are the project manager of HFD project. You have identified several project risks. You have adopted alternatives to deal with these risks

This is a dedicated watch page for a single video.

Full Certification Question

You are the project manager of HFD project. You have identified several project risks. You have adopted alternatives to deal with these risks which do not attempt to reduce the probability of a risk event or its impacts. Which of the following response have you implemented?