Video: Wendy has identified a risk event in her project isaca video

Question 1 Be Honest
« Back   Next isaca crisc Exam Question »
Answer

Full Certification Question

Wendy has identified a risk event in her project that has an impact of $75,000 and a 60 percent chance of happening. Through research, her project team learns that the risk impact can actually be reduced to just $15,000 with only a ten percent chance of occurring. The proposed solution will cost $25,000. Wendy agrees to the $25,000 solution. What type of risk response is this?