AWS Exams GCP Exams Azure Exams GitHub Exams Jira Exams ISC2 Exams

Video: Sammy is the project manager for her isaca video

Question 1
« Back   Next crisc Question »

Full Certification Question

Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?