Full Certification Question

You are the project manager of GFT project. Your project involves the use of electrical motor. It was stated in its specification that if its temperature would increase to 500 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. If the machine overheats even once it will delay the project's arrival date. So to prevent this you have decided while creating response that if the temperature of the machine reach 450, the machine will be paused for at least an hour so as to normalize its temperature. This temperature of 450 degrees is referred to as?