Video: Harry works as a project manager for the NHQ isaca video

Question 1 Be Honest
« Back   Next isaca crisc Question »
Answer

Full Certification Question

Harry works as a project manager for the NHQ Project. He is performing quantitative risk analysis for his project. One of the project risks has a 40 percent probability of happening, and it will cost the project $65,000 if the risk happens. What is the expected monetary value of this risk event?