crisc video for john works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the

This is a dedicated watch page for a single video.

Full Certification Question

John works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk?