crisc video for you work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed

Full Certification Question

You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request.Where should the declined change request be documented and stored?