Video upload date:  · Duration: PT1H46M27S  · Language: EN

You work as a project manager for BlueWell Inc isaca video

crisc video for you work as a project manager for BlueWell Inc. You are preparing for the risk identification process. You will need to involve several of the

This is a dedicated watch page for a single video.

Full Certification Question

You work as a project manager for BlueWell Inc. You are preparing for the risk identification process. You will need to involve several of the project's key stakeholders to help you identify and communicate the identified risk events. You will also need several documents to help you and the stakeholders identify the risk events. Which one of the following is NOT a document that will help you identify and communicate risks within the project?