You work as a project manager for BlueWell Inc isaca video
crisc video for you work as a project manager for BlueWell Inc. You are preparing for the risk identification process. You will need to involve several of the
            Question 1
            Be Honest
          
          
        Answer
          Full Certification Question
You work as a project manager for BlueWell Inc. You are preparing for the risk identification process. You will need to involve several of the project's key stakeholders to help you identify and communicate the identified risk events. You will also need several documents to help you and the stakeholders identify the risk events. Which one of the following is NOT a document that will help you identify and communicate risks within the project?