The CTO of your company is concerned about the gcp video

 ·  PT1H46M27S  ·  EN

data-engineer-pro video for the CTO of your company is concerned about the costs of running data pipelines, especially some large batch processing jobs. The

Full Certification Question

The CTO of your company is concerned about the costs of running data pipelines, especially some large batch processing jobs. The jobs do not have to be run on a fixed schedule and the CTO is willing to wait longer for jobs to complete if it can reduce costs. You are using Cloud Dataflow for most pipelines and would like to cut costs but not make any more changes than necessary. What would you recommend?