Video: A company leases data center space in a aws video

Question 1 Be Honest
« Back   Next solutions-architect-pro Certification Question »
Answer

Full Certification Question

A company leases data center space in a co-location facility and needs to move out before the end of the financial year in 90 days. The company currently runs 150 virtual machines and a NAS device that holds over 50 TB of data. Access patterns for the data are infrequent but when access is required it must be immediate. The VM configurations are highly customized. The company has a 1 Gbps internet connection which is mostly idle and almost completely unused outside of business hours. Which combination of steps should a Solutions Architect take to migrate the VMs to AWS with minimal downtime and operational impact? (Select TWO.)